Skip to content
Adams
PhosphateFluid PowerCase study · November 8, 2024 · 6 min read

How a phosphate processor cut $120k a year in compressed-air losses without buying a single new compressor

Headline result$120kannual electricity savings
Industrial chemical processing plant exterior with stacks at dusk
Industrial chemical processing plant exterior with stacks at dusk
Customer profile

A 40,000 sq ft phosphate processing plant near Lakeland, Florida. Three reactor trains, continuous 24/6 operation, one of the largest single consumers of compressed air on the customer's site map.

Capability

Fluid Power

Partner brands

MAC Valves · Camozzi · Festo

01

The problem

Plant engineering had been running the rotary-screw compressor house at 98% load for the better part of two years. The reliability team was watching loaded-hour curves climb, two of the four 200 hp units were lined up for top-end overhauls, and the capital request for a fifth compressor was already drafted at $340,000 plus install. Then a control-system upgrade flagged the obvious next step: get an independent set of eyes on the air side before adding capacity.

We brought a two-person crew on-site for a 48-hour ultrasonic leak survey across the entire phosphate train — feed, react, granulate, screen, bag. Findings: 187 distinct compressed-air leaks, weighted by orifice size and dwell. Combined leak load measured at the equivalent of 142 SCFM, or about 38% of the rated output of one of the four compressors. Roughly $9,800 a month at the customer's blended electrical rate.

“We came in expecting to size a fifth compressor. We left with a $340,000 capital line item we don't need to spend.”
— Plant reliability manager, phosphate processing
02

What we did

Rather than dump the survey on the maintenance team and walk away, we ranked every leak by ease (tag-and-replace vs. rebuild) and dollars-per-hour (size + duty cycle). The top 30 leaks alone accounted for 71% of the total loss. We supplied the replacement push-to-connect fittings, FRL kits, and quick-disconnects directly from MAC, Camozzi, and Festo stock and rode along for the first two days of the patch campaign so the night-shift millwrights could see the technique.

Phase two: replaced 14 worn-out poppet valves on the bagger line with MAC 92-series pulse valves and rebuilt three filter-regulator-lubricator stations near the granulator. We also tagged 23 lower-priority leaks for the next planned outage. Total parts and labor for phase one and two came in at $61,000.

03

The result

Six weeks after the patch campaign, ultrasonic resurvey measured leak load at 19 SCFM — an 87% reduction. The plant pulled one of the 200 hp compressors offline and put it on standby; the capital request for the fifth compressor was withdrawn. Verified annualized savings: $118,400 in electricity and $14,000 in deferred compressor maintenance. ROI on the engagement: 4.7 months.

$120k
annual electricity savings
87%
leak load reduction
4.7 mo
ROI payback
04

Components used

  • 92-series pulse valves MAC Valves
  • Push-to-connect fittings, polyurethane tubing Camozzi
  • FRL combo units Festo
  • Ultrasonic leak detection (UE Systems)

Other recent work

All case studies →
Get on the schedule

Have a problem on a line right now?

Tell us where it hurts. A senior application engineer will respond within one business day — same-day for true downtime emergencies.

On-site responseSame day in the Tampa Bay area
Average audit2 days on the floor · 10-day report
Engineering staff27 application & field engineers
LanguagesEnglish & Spanish, in-territory